How to Install Roots Blower
How to Install Roots Blower
Proper installation of a roots blower is critical for reliable operation and long service life. Based on commissioning experience across hundreds of installations, 60% of field problems trace to installation errors – improper foundation, pipe strain, misalignment, or electrical issues. A correct installation prevents bearing failure, vibration, and premature wear.
This guide provides a step-by-step procedure for installing a roots blower – from foundation preparation to pre-commissioning checks. Follow these guidelines to ensure reliable operation.
Table of Contents
What Does a Roots Blower Installation Involve?
Pre-Installation Planning
Step 1: Foundation Preparation
Step 2: Blower Placement and Leveling
Step 3: Piping Installation
Step 4: Coupling and Alignment
Step 5: Electrical Connections
Step 6: Oil and Lubrication
Step 7: Pre-Commissioning Checks
Step 8: Start-Up
Common Installation Mistakes
Frequently Asked Questions
Final Thoughts
What Does a Roots Blower Installation Involve?
A roots blower installation includes foundation preparation, blower placement, piping connections, coupling alignment, electrical wiring, and pre-commissioning checks. Proper installation is essential for reliability and longevity.
Installation steps:
Foundation preparation
Blower placement and leveling
Piping installation (inlet and discharge)
Coupling and alignment
Electrical connections
Oil and lubrication
Pre-commissioning checks
Start-up
Based on field data, a proper installation takes 1–2 days for a packaged unit and 2–3 days for field-assembled components.
Pre-Installation Planning
Before starting installation:
1. Review documentation.
Installation manual
Dimensional drawings
P&ID (piping and instrumentation diagram)
Electrical schematics
Foundation drawings
2. Verify equipment.
Check model and serial number
Inspect for shipping damage
Verify accessories are included
Check motor voltage and frame
3. Prepare site.
Clean area
Verify foundation is ready
Check overhead clearance
Plan lifting and rigging
4. Gather tools.
Laser alignment tool (preferred) or dial indicators
Torque wrench
Level (precision)
Wrenches and sockets
Lifting equipment (crane, hoist, slings)
5. Review safety requirements.
Lock-out/tag-out procedures
Lifting safety
Personal protective equipment (PPE)
Step 1: Foundation Preparation
Foundation requirements:
Rigid concrete or steel base
Minimum mass: 3× blower weight
Level surface (within 0.002 inches per foot)
Anchor bolts embedded or epoxied
Concrete foundation:
Pour concrete with anchor bolts in place
Allow curing (minimum 7 days)
Grout under base frame (if required)
Surface must be level and smooth
Steel foundation:
Fabricate from structural steel
Weld or bolt to building structure
Must be rigid – no flexing
Foundation checklist:
Foundation mass ≥ 3× blower weight
Surface level within 0.002 inches/ft
Anchor bolts in correct position
Grout under base frame (if required)
Foundation cured (concrete)
Step 2: Blower Placement and Leveling
Placing the blower:
Lift blower with appropriate rigging
Lower onto foundation or base frame
Align with anchor bolts
Install nuts and washers (finger tight)
Leveling:
Place precision level on machined surfaces
Check level in both directions (longitudinal and transverse)
Adjust using leveling bolts or shims
Recheck level – within 0.002 inches per foot
Tightening:
Tighten anchor bolts to specified torque
Recheck level (bolts can shift alignment)
Record final level readings
Placement checklist:
Lifting equipment rated for weight
Blower aligned with anchor bolts
Level within 0.002 inches per foot
Anchor bolts torqued to specification
Final level verified
Step 3: Piping Installation
General piping rules:
Flexible connectors within 18 inches of both inlet and discharge flanges
Support piping independently – do not use blower casing as support
No pipe strain on flanges
Slope piping to drain (if applicable)
Clean piping before connection (remove debris)
Inlet piping:
Install flexible connector within 18 inches of inlet flange
Support piping separately
Install inlet filter before flexible connector
Install inlet silencer (if applicable)
Check for vacuum-rated filter
Discharge piping:
Install flexible connector within 18 inches of discharge flange
Support piping separately
Install check valve within 3 feet of discharge
Install relief valve between blower and check valve
Install discharge silencer (if applicable)
Piping checklist:
Flexible connectors within 18 inches
Piping independently supported
No pipe strain on flanges
Inlet filter installed
Check valve installed (discharge)
Relief valve installed (between blower and check valve)
Piping clean before connection
Step 4: Coupling and Alignment
Coupling installation:
Verify coupling halves are clean
Install coupling on motor shaft
Install coupling on blower shaft
Install coupling guard (safety)
Alignment requirements:
Parallel offset: ≤0.002 inches (0.05 mm)
Angular misalignment: ≤0.001 inches per inch
Follow coupling manufacturer specifications
Alignment methods:
Laser alignment (best – fastest, most accurate)
Dial indicator (traditional, accurate)
Straight edge and feeler gauge (least accurate, not recommended)
Alignment procedure:
Mount laser alignment tool or dial indicators
Measure parallel and angular misalignment
Adjust motor using shims
Recheck alignment
Tighten motor bolts
Recheck alignment (bolts can shift)
Alignment checklist:
Coupling clean and installed
Parallel offset ≤0.002 inches
Angular misalignment ≤0.001 inches/in
Alignment rechecked after tightening
Coupling guard installed
Step 5: Electrical Connections
Motor wiring:
Verify motor voltage matches supply
Connect power leads to motor terminals
Connect ground wire
Install conduit or cable tray
Verify overload protection is sized correctly
Control wiring:
Connect pressure switch (if applicable)
Connect temperature switch (if applicable)
Connect VFD control wiring (if applicable)
Connect remote start/stop (if applicable)
VFD installation (if applicable):
Locate VFD in clean, dry area
Ambient temperature below 104°F
Provide adequate ventilation
Install line reactor (reduce harmonics)
Install output reactor (protect motor)
Use shielded motor cable
Proper grounding
Electrical checklist:
Voltage verified
Connections tight
Ground wire connected
Overload protection sized correctly
VFD installed correctly (if applicable)
Control wiring connected
Step 6: Oil and Lubrication
Oil type:
Synthetic ISO VG 150 or 220 (check manufacturer specification)
Do not mix synthetic and mineral oil
Oil filling:
Remove fill plug
Fill with correct oil to sight glass midpoint
Install fill plug
Oil level:
Check with blower level and stopped
Oil level at middle of sight glass
Oil checklist:
Correct oil type used
Oil level at sight glass midpoint
No overfilling
Step 7: Pre-Commissioning Checks
Before start-up:
Mechanical checks:
All bolts tight (foundation, motor, blower)
Coupling guard installed
Piping supported
No pipe strain
Belt tension (if belt drive)
Rotation direction verified (manual check)
Electrical checks:
Voltage verified
Wiring correct
Ground connected
Overload protection set correctly
Motor rotation direction checked (jog motor)
System checks:
Inlet filter installed
Check valve installed (discharge)
Relief valve installed and set
Pressure gauge installed
Temperature gauge installed
All valves open
Safety checks:
Lock-out/tag-out removed
Guards in place
Area clear of personnel
Fire extinguisher available
Step 8: Start-Up
Start-up procedure:
Jog motor. Briefly start motor to verify rotation direction. Correct by swapping two motor leads if needed.
Run unloaded. Run blower for 5–10 minutes with no load (relief valve open or discharge open). Check for unusual noise or vibration.
Check oil level. Stop blower, check oil level. Add oil if needed.
Load blower. Gradually close discharge valve or allow system to pressurize. Monitor pressure and temperature.
Check alignment. After first hour of operation, check coupling alignment. Thermal expansion can change alignment.
Record baseline readings. Pressure, temperature, vibration, motor amps. Record for future reference.
Start-up checklist:
Rotation direction verified
No unusual noise or vibration
Oil level checked and corrected
Pressure within design range
Temperature below 220°F
Alignment rechecked after warm-up
Baseline readings recorded
Common Installation Mistakes
1. No flexible connectors.
Hard piping causes pipe strain and misalignment. Always use flexible connectors within 18 inches.
2. Piping not supported.
Pipe weight on blower casing causes distortion and misalignment. Support piping independently.
3. Poor alignment.
Misalignment causes bearing failure and vibration. Align to ≤0.002 inches parallel.
4. No check valve.
Backspin damages timing gears. Install check valve on discharge.
5. No relief valve.
Overpressure damages blower. Install relief valve between blower and check valve.
6. Wrong oil.
Incorrect oil causes bearing failure. Use specified oil.
7. Overfilling oil.
Overfilling causes foaming and overheating. Fill to sight glass midpoint.
8. No rotation direction check.
Wrong rotation damages timing gears. Check rotation before loading.
Frequently Asked Questions
1. How long does roots blower installation take?
Packaged unit: 1–2 days. Field-assembled components: 2–3 days. Includes foundation, piping, alignment, electrical, and pre-commissioning. Larger blowers or complex systems may take longer.
2. What foundation is required?
Rigid concrete or steel base. Minimum mass: 3× blower weight. Surface level within 0.002 inches per foot. Anchor bolts embedded or epoxied.
3. What alignment is required?
Parallel offset ≤0.002 inches (0.05 mm). Angular misalignment ≤0.001 inches per inch. Laser alignment is preferred – faster and more accurate.
4. What oil should I use?
Synthetic ISO VG 150 or 220. Check manufacturer specification. Do not mix synthetic and mineral oil.
5. Why are flexible connectors required?
Flexible connectors prevent pipe strain on blower flanges. Thermal expansion and vibration are isolated from the blower. Install within 18 inches of both inlet and discharge flanges.
6. Where should the check valve be installed?
On discharge piping, within 3 feet of blower flange. Prevents backspin when blower stops – backspin damages timing gears.
7. Where should the relief valve be installed?
Between blower and check valve. Set at operating pressure + 2 psig. Protects against overpressure.
8. Why is alignment important?
Misalignment causes bearing failure and vibration. Proper alignment extends bearing life by 2–3×.
9. How do I check rotation direction?
Jog the motor briefly. Check rotation arrow on blower casing. Swap any two motor leads if rotation is wrong.
10. What baseline readings should I record?
Discharge pressure, discharge temperature, motor amps, vibration (overall), oil level. Record after start-up for future reference.
11. Can I install a roots blower outdoors?
Yes – with weather protection. Install shelter or cover. Provide cooling air – avoid recirculating hot air.
12. What is the recommended piping material?
Carbon steel for standard applications. Stainless steel for corrosive gas. Schedule 40 minimum. Use flexible connectors.
13. How do I check for pipe strain?
Check flanges for gap or misalignment. Piping should not force blower out of alignment. Use dial indicator on flanges.
14. What is the minimum clearance around the blower?
36 inches on all sides for maintenance access. 60 inches above for lifting.
15. Do I need a VFD?
VFD is recommended for variable flow applications. Saves energy 25–35%. Specify inverter-duty motor with VFD.
Final Thoughts
After commissioning hundreds of roots blower installations, here is my practical advice:
Foundation is critical. A rigid foundation prevents misalignment and vibration. Mass at least 3× blower weight. Level within 0.002 inches per foot.
Piping must be supported independently. Pipe weight on the blower causes distortion and misalignment. Use flexible connectors within 18 inches of both flanges.
Alignment matters. Misalignment is the leading cause of bearing failure. Align to ≤0.002 inches parallel. Laser alignment is fastest and most accurate.
Check rotation direction before loading. Wrong rotation damages timing gears. Jog the motor and check the arrow.
Record baseline readings. Pressure, temperature, vibration, motor amps. Baseline data helps troubleshoot future problems.
The bottom line. Proper installation is the foundation of reliable roots blower operation. Zhanggu and other manufacturers provide installation manuals. Follow the steps. Take the time to do it right. A correct installation prevents 60% of field problems.



